South Leschi Moorage Update

11 minutes ago
2 min read

South Leschi Moorage: From Underground Utilities to On-the-Water Construction

After months of construction - and a few surprises along the way - the South Leschi Moorage project is making steady progress. Work on underground utilities is nearing completion, the parking lot is getting closer to restoration, and marine construction is scheduled to begin in December.

One particularly welcome piece of news involves the underground fuel storage tank unexpectedly discovered during utility work this fall. The abandoned tank was successfully removed, and testing found no contamination in the surrounding soil. The discovery delayed construction by about a week, but given the potential complications associated with an old underground fuel tank, the project team says this was about as good an outcome as could have been hoped for.

Utility work in the parking lot has also moved forward. The sewer line has been approved for cover, waterline installation is complete and awaiting a pre-cover inspection from Seattle Public Utilities, and electrical work is finished except for the light-pole bases.

Once the required City agencies have approved the work, crews can begin backfilling and restoring the surface. The current schedule calls for utility work to wrap up shortly, followed by resurfacing, although November weather could affect the timing. Seattle Parks and Recreation says reopening the parking lot as soon as possible remains a priority.

Neighbors may also have noticed a change to parking along the Parks-owned portion of Lakeside Avenue. According to the project manager, changing those spaces to a two-hour maximum appears to have helped improve parking availability.


Next up: the marina itself

While much of the recent construction has been happening underground - or completely out of sight - major pieces of the new marine facility have been taking shape elsewhere.

The breakwater floats, steel-tub walkway floats, gangways, piles and sewage pump-out station have now been fabricated or procured, with other offsite fabrication nearing completion.

Manson Construction is scheduled to mobilize at South Leschi Moorage on December 15, when the project will enter a much more visible phase. Demolition work is expected during December, followed by construction of the new marine facility beginning in January.

That should give neighbors something considerably more interesting to watch than underground utility work. As the project manager put it, marine construction can be fun to watch - and folks of all ages may enjoy seeing the large floats, piles, and other components of the new marina arrive and be put into place.

After a year in which construction impacts and parking concerns generated plenty of neighborhood discussion, the latest update offers encouraging signs of progress: the unexpected fuel tank is safely out of the ground, utility work is nearing completion, major marine components are ready, and the project is moving toward the phase when the new South Leschi Moorage will finally begin to take shape on the water.



 
 
 